Get 2026 Updated Free PMI PMI-RMP Exam Questions & Answer [Q39-Q63]

Share

Get 2026 Updated Free PMI PMI-RMP Exam Questions and Answer

PMI-RMP Dumps PDF and Test Engine Exam Questions


PMI-RMP exam covers a wide range of topics related to risk management, including risk identification, risk analysis and assessment, risk response planning, risk monitoring and control, and risk communication. PMI-RMP exam is a computer-based test and consists of 170 multiple-choice questions, which must be completed within a 3.5-hour time frame.


PMI-RMP certification is ideal for professionals who work in industries that require a high level of risk management, such as construction, healthcare, finance, and information technology. PMI Risk Management Professional certification is also suitable for project managers and risk management professionals who want to enhance their skills and increase their career opportunities. By obtaining the PMI-RMP certification, professionals can demonstrate their expertise in risk management and gain a competitive edge in the job market.


To be eligible for the PMI-RMP exam, candidates must have a minimum of three years of professional experience in risk management and 40 hours of risk management education. Candidates must also have a high school diploma or global equivalent. However, individuals with a bachelor's or master's degree may be eligible for a reduced number of required hours of experience and education.

 

NEW QUESTION # 39
The risk manager examines the enterprise environmental factors to gain an understanding of the stakeholders' risk appetite. However, risk appetites are not determined.
What is the best method a risk manager should use to initially define the stakeholders' risk appetite?

  • A. Meetings and interviews with key stakeholders.
  • B. What-if scenario.
  • C. Conduct SWOT analysis.
  • D. Review risk response strategies

Answer: A


NEW QUESTION # 40
A risk manager of a complex project has identified a risk and believes a deeper understanding of the source and likelihood is necessary. How should the risk manager proceed?

  • A. Perform a review of project documents
  • B. Create prompt lists for expert interviews
  • C. Analyze the assumptions and constraints
  • D. Develop and employ an Ishikawa diagram

Answer: D

Explanation:
An Ishikawa diagram (also known as a fishbone or cause-and-effect diagram) is a tool used to identify and analyze the root causes and sources of a risk. It helps the risk manager gain a deeper understanding of the risk source and likelihood. (Reference: PMBOK Guide, 6th Edition, p. 139) An Ishikawa diagram, also known as a fishbone diagram or a cause-and-effect diagram, is a tool that can help the risk manager to analyze the root causes of a risk and to identify the factors that influence its occurrence and impact. An Ishikawa diagram can also help to visualize the relationships among different causes and to prioritize the most significant ones. By developing and employing an Ishikawa diagram, the risk manager can gain a deeper understanding of the source and likelihood of the risk and plan appropriate responses accordingly. References: The Standard for Risk Management in Portfolios, Programs, and Projects, page 72; PMBOK Guide, 6th edition, page 398.


NEW QUESTION # 41
An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification.
What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)

  • A. Conduct interviews, meetings, and focus groups
  • B. Employ brainstorming to generate spontaneous ideas
  • C. Develop checklists based on historical information
  • D. Assign a different risk manager for each portfolio unit
  • E. Perform qualitative and quantitative risk analyses

Answer: A,B,C


NEW QUESTION # 42
There are five inputs to the quantitative risk analysis process. Which one of the following is NOT an input to the perform quantitative risk analysis process?

  • A. Cost management plan
  • B. Enterprise environmental factors
  • C. Risk management plan
  • D. Risk register

Answer: B


NEW QUESTION # 43
A project team in a multinational organization is working on a risk management plan for a multimillion-dollar project. This project involves three global regions with a wide range of critical stakeholders with varying degrees of risk appetite.
What should the risk manager advise the project team to do?

  • A. Align the project risk thresholds with the organizational risk appetite.
  • B. Concentrate on the risk appetites of the vulnerable stakeholders.
  • C. Align the project risk thresholds with the risk appetite of a critical region.
  • D. Concentrate on the risk appetites of the influential stakeholders.

Answer: A

Explanation:
When managing risks in a project that spans multiple regions with varying degrees of risk appetite, it is essential to align the project's risk thresholds with the organization's overall risk appetite. This approach ensures consistency across all regions and projects, particularly in multinational organizations where varying regional practices and risk appetites could create discrepancies. By aligning with the organizational risk appetite, the project team ensures that the risk management process adheres to the strategic objectives and governance framework set by the organization. This alignment also helps in managing stakeholder expectations and ensuring that the project remains within acceptable risk parameters set by the organization as a whole, as emphasized in the Risk Management Policy.


NEW QUESTION # 44
You and your project team are identifying the risks that may exist within your project. Some of the risks are small risks that won't affect your project much if they happen. What should you do with these identified risk events?

  • A. These risks can be added to a low priority risk watch list.
  • B. All risks must have a valid, documented risk response.
  • C. These risks can be dismissed.
  • D. These risks can be accepted.

Answer: A


NEW QUESTION # 45
Your organization has named you the project manager of the JKN Project. This project has a BAC of $1,500,000 and it is expected to last 18 months. Management has agreed that if the schedule baseline has a variance of more than five percent then you will need to crash the project. What happens when the project manager crashes a project?

  • A. The project will take longer to complete, but risks will diminish.
  • B. The amount of hours a resource can be used will diminish.
  • C. Project risks will increase.
  • D. Project costs will increase.

Answer: D


NEW QUESTION # 46
A project with impending risks has 12 deliverables as subprojects, which will be executed in three different locations involving multiple stakeholders. What should the risk manager do to organize the prevailing risks?

  • A. Use focus groups to conduct group risk assessments of the project to identify risks.
  • B. Request individual assessments of the project and its deliverables to identify risks.
  • C. Use the external risk assessment of the project and its deliverables to identify risks.
  • D. Combine individual and focus groups to identify risks and create the overall risk register.

Answer: D

Explanation:
In complex projects with multiple deliverables, locations, and stakeholders, best practice is to combine individual risk identification (e.g., interviews, surveys) with group-based methods (e.g., focus groups, workshops) to ensure comprehensive risk coverage and diverse input. According to the PMBOK Guide:
"Both individual and group risk identification techniques are valuable. Combining interviews (individual) with facilitated workshops or focus groups (group) can help identify risks at all levels and build a comprehensive risk register for the overall project."
- PMBOK Guide, 6th Edition, Section 11.2.2.2 (Data Gathering: Interviews, Facilitation) ISO 31000 also recommends a mix of approaches to ensure risks are not overlooked due to limited perspectives.
References:
PMBOK Guide, 6th Edition, Section 11.2.2.2
ISO 31000:2018, Section 6.4


NEW QUESTION # 47
A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described. What is critical for the risk manager to consider when describing the causes?

  • A. The causes must be validated by the risk owner
  • B. The causes represent actual conditions
  • C. Each cause has well defined owner
  • D. Each cause has a degree of uncertainty

Answer: B

Explanation:
When describing the causes of a risk, it is critical for the risk manager to ensure that the causes represent actual conditions, as this will help in the accurate identification and assessment of the.
According to the PMBOKGuide, a risk is defined as "an uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives" (page 720). A risk can be described by its causes, effects, and probability of occurrence. The causes are the factors or circumstances that give rise to the risk, and they should represent the actual conditions that exist or may exist in the project environment. The causes should not be based on assumptions, opinions, or speculations, but on facts, evidence, or data. Therefore, option C is the correct answer.
Option A is incorrect because not every cause has a degree of uncertainty. Some causes may be certain or deterministic, such as contractual obligations, regulatory requirements, or physical laws. Uncertainty is a characteristic of the risk itself, not the cause.
Option B is incorrect because not every cause has a well-defined owner. The owner is the person or entity who is assigned the responsibility and authority to manage the risk, not the cause. The owner should be identified after the risk is analyzed and prioritized, not before.
Option D is incorrect because the causes do not need to be validated by the risk owner. The risk owner is the person or entity who is accountable for the risk response, not the risk identification. The causes should be validated by the risk manager or the risk identification team, who are responsible for collecting and documenting the risk information.


NEW QUESTION # 48
During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.
Which action should the risk manager take to address this risk?

  • A. Accept the identified risk because other stakeholders feel that there are higher priority risks to address.
  • B. Escalate the identified risk to the project sponsor and allow them to determine the best course of action.
  • C. Add the identified risk to the risk register for future probability and impact analysis.
  • D. Mitigate the identified risk in order to reduce the probability of impacting the stakeholder's team.

Answer: C

Explanation:
Adding the identified risk to the risk register is the best action that the risk manager can take to address this risk. The risk register is a document that records the identified risks, their characteristics, their status, and their responses. By adding the risk to the risk register, the risk manager can ensure that the risk is not overlooked or ignored, and that it will be subjected to further probability and impact analysis to determine its priority and response strategy. Accepting the identified risk because other stakeholders feel that there are higher priority risks to address is not a good practice, as it may lead to overlooking a potentially significant risk that could affect the stakeholder's team. Mitigating the identified risk in order to reduce the probability of impacting the stakeholder's team is not advisable, as it may be a premature or unnecessary action without proper analysis of the risk probability and impact. Escalating the identified risk to the project sponsor and allowing them to determine the best course of action is not appropriate, as it may be an overreaction or a sign of lack of competence from the risk manager, who should be able to handle the risk identification and analysis process. References: PMI Risk Management Professional (PMI-RMP)Exam Content Outline1, PMI Practice Standard for Project Risk Management2, Risk Management Professional (PMI-RMP)Cert Guide3


NEW QUESTION # 49
Ben works as a project manager for the MJH Project. In this project, Ben is preparing to identify stakeholders so he can communicate project requirements, status, and risks. Ben has elected to use a salience model as part of his stakeholder identification process. Which of the following activities best describes a salience model?

  • A. Describing classes of stakeholders based on their power (ability to impose their will), urgency (need for immediate attention), and legitimacy (their involvement is appropriate).
  • B. Grouping the stakeholders based on their level of authority ("power") and their active involvement ("influence") in the project.
  • C. Grouping the stakeholders based on their level of authority ("power") and their level or concern ("interest") regarding the project outcomes.
  • D. Influence/impact grid, grouping the stakeholders based on their active involvement ("influence") in the project and their ability to affect changes to the project's planning or execution ("impact").

Answer: A


NEW QUESTION # 50
Nancy is the project manager of the NHH project. She and the project team have identified a significant risk in the project during the qualitative risk analysis process. Bob is familiar with the technology that the risk is affecting and proposes to Nancy a solution to the risk event. Nancy tells Bob that she has noted his response, but the risk really needs to pass through the quantitative risk analysis process before creating responses. Bob disagrees and ensures Nancy that his response is most appropriate for the identified risk. Who is correct in this scenario?

  • A. Bob is correct. Not all risk events have to pass the quantitative risk analysis process to develop effective risk responses.
  • B. Nancy is correct. All risks of significant probability and impact should pass the quantitative risk analysis process before risk responses are created.
  • C. Nancy is correct. Because Nancy is the project manager she can determine the correct procedures for risk analysis and risk responses. In addition, she has noted the risk response that Bob recommends.
  • D. Bob is correct. Bob is familiar with the technology and the risk event so his response should be implemented.

Answer: A


NEW QUESTION # 51
Your project uses a piece of equipment that if the temperature of the machine goes above 450 degree Fahrenheit the machine will overheat and have to be shut down for 48 hours. Should this machine overheat even once it will delay the project's end date. You work with your project to create a response that should the temperature of the machine reach 430, the machine will be paused for at least an hour to cool it down. The temperature of 430 is called what?

  • A. Risk response
  • B. Risk identification
  • C. Risk event
  • D. Risk trigger

Answer: D

Explanation:
Explanation/Reference:


NEW QUESTION # 52
A project is evaluating a new software to streamline the current purchase order process. The current process is labor-intensive and involves printing, ink signatures, scanning, and emailing. Several team members gathered cycle time data to gauge the current process and evaluate the new process.
What should the risk manager do next with the data set?

  • A. Perform Monte Carlo simul-ations
  • B. Perform a probability and impact assessment
  • C. Perform a sensitivity analysis
  • D. Perform a risk data quality assessment

Answer: D

Explanation:
After gathering cycle time data, the risk manager should perform a risk data quality assessment to ensure the data is accurate, reliable, and relevant for evaluating the current process and the new software.
A risk data quality assessment is a technique to evaluate the degree to which the data about risks is useful and accurate for risk management. It involves examining the reliability, credibility, accuracy, and validity of the data collected. A risk data quality assessment can help the risk manager to determine the confidence level of the risk analysis and the quality of the risk responses. Performing a risk data quality assessment is the next logical step after gathering the cycle time data, as it will help to ensure that the data is suitable for further analysis and decision making. References: PMI Risk Management Professional (PMI-RMP) Examination Content Outline and Specifications1, page 9; A Guide to the Project Management Body of Knowledge (PMBOKGuide) - Sixth Edition, page 397.


NEW QUESTION # 53
A risk manager reviews a Monte Carlo schedule risk analysis model before sharing the results with the project manager. The risk manager notices that activity correlations were not included in the model.
What is an effect of adding the correlation to the model?

  • A. Increases the probability of correlated activities finishing on time.
  • B. Allows more risks to be included in the model.
  • C. Increases the standard deviation of the model.
  • D. Reduces the project completion duration.

Answer: C

Explanation:
Explanation
Adding correlation to the model accounts for the relationship between activities, which can result in increased variability in the model's outcomes. This will increase the standard deviation, which is a measure of the uncertainty in the model.
According to the PMBOK Guide, 6th edition, Chapter 11: Project Risk Management1, an effect of adding the correlation to the Monte Carlo schedule risk analysis model is that it increases the standard deviation of the model. This is because:
Correlation is the statistical relationship between two or more variables. In a schedule risk analysis, correlation can be used to model the dependency between the durations of different activities. For example, if two activities are positively correlated, it means that if one activity takes longer than expected, the other activity is also likely to take longer than expected. Conversely, if two activities are negatively correlated, it means that if one activity takes longer than expected, the other activity is likely to take shorter than expected.
A Monte Carlo schedule risk analysis is a simulation technique that uses random values for uncertain variables, such as activity durations, to generate possible outcomes for the project schedule. The simulation is repeated many times to produce a probability distribution of the project completion date and duration. The standard deviation is a measure of the variability or dispersion of the distribution. A higher standard deviation means that the distribution is more spread out and less predictable.
Adding correlation to the Monte Carlo schedule risk analysis model increases the standard deviation of the model because it introduces more variability and uncertainty to the simulation. Correlated activities can have a cumulative effect on the project schedule, either positively or negatively, depending on the direction and strength of the correlation. This can result in more extreme outcomes for the project completion date and duration, which increase the spread of the distribution and the standard deviation.
References:
PMBOK Guide, 6th edition, Chapter 11: Project Risk Management1
Risk Management Professional (PMI-RMP) Exam Cert Guide2


NEW QUESTION # 54
Adrian is the project manager of the NHP Project. In her project there are several work packages that deal with electrical wiring. Rather than to manage the risk internally she has decided to hire a vendor to complete all work packages that deal with the electrical wiring. By removing the risk internally to a licensed electrician Adrian feels more comfortable with project team being safe.
What type of risk response has Adrian used in this example?

  • A. Acceptance
  • B. Mitigation
  • C. Transference
  • D. Avoidance

Answer: C


NEW QUESTION # 55
You work as a project manager for BlueWell Inc. You have declined a proposed change request because of the risk associated with the proposed change request. Where should the declined change request be documented and stored?

  • A. Project document updates
  • B. Project archives
  • C. Lessons learned
  • D. Change request log

Answer: D


NEW QUESTION # 56
A newly assigned project manager is reviewing the project documents with stakeholders to identify opportunities that will fast track the project and realize the financial benefits of early completion. What document should be updated at the end of the review?

  • A. Risk response plan
  • B. Risk management plan
  • C. Risk identification plan
  • D. Risk register

Answer: B


NEW QUESTION # 57
A risk manager is preparing risk reports to be included in the monthly status report for project executives.
How should the risk manager present the information?

  • A. A risk burndown chart showing remaining risks
  • B. The format established in the risk management plan
  • C. Earned value management (EVM) variance metrics
  • D. An itemized list of remaining risks and their scores

Answer: B

Explanation:
When preparing risk reports for inclusion in the monthly status report for project executives, the risk manager should adhere to the format established in the risk management plan. This ensures consistency, clarity, and alignment with the overall project management framework, making it easier for executives to understand and assess the information. PMI emphasizes the importance of following established communication protocols and formats in risk reporting to maintain effective stakeholder engagement.


NEW QUESTION # 58
A new risk manager is assigned to an ongoing project, what should the new risk manager dofirst to assess the project environment?

  • A. Review the scope of work to determine the prescribed project methodology.
  • B. Review the policies and practices that are outlined in the risk management plan.
  • C. Review potential next steps with the project team.
  • D. Review the contract and determine the resources and project funding.

Answer: B

Explanation:
Explanation
When a new risk manager is assigned to an ongoing project, their first step should be to review the existing risk management plan to understand the current policies, practices, and strategies in place.


NEW QUESTION # 59
Your project uses a piece of equipment that if the temperature of the machine goes above 450 degree Fahrenheit the machine will overheat and have to be shut down for 48 hours. Should this machine overheat even once it will delay the project's end date. You work with your project to create a response that should the temperature of the machine reach 430, the machine will be paused for at least an hour to cool it down. The temperature of 430 is called what?

  • A. Risk response
  • B. Risk identification
  • C. Risk event
  • D. Risk trigger

Answer: D


NEW QUESTION # 60
A company has implemented a policy requirement for employees to use complex passwords and update them regularly. A few employees are unable to make the changes, which increases the likelihood of cybercriminals compromising their passwords.
What should the risk manager do?

  • A. Reassess the residual risk level.
  • B. Reassess the inherent risk level.
  • C. Increase the residual risk monitoring.
  • D. Increase the inherent risk monitoring.

Answer: A

Explanation:
Residual risk refers to the remaining risk after implementing risk responses or controls. In this scenario, despite the policy requiring complex passwords and regular updates, some employees' inability to comply increases the likelihood of password compromise. This non-compliance elevates the residual risk beyond acceptable levels. The risk manager should reassess the residual risk to determine its current status and evaluate whether additional controls or actions are necessary to mitigate the heightened threat. This reassessment ensures that the organization's risk management strategies remain effective and aligned with its security objectives.
PMI Risk Management Study Guide References:
The PMI-RMP Exam Preparation Study Guide defines residual risk as "the risk that remains after risk responses have been implemented," highlighting the need for continuous monitoring and reassessment to address any changes in risk exposure.


NEW QUESTION # 61
A project manager is educating the project team on risk management regarding the role of threats and opportunities. The team decides to log the opportunities in the current project's risk register to try to maximize their chances of occurrence.
What should the project team do next?

  • A. Log the threats in the risk register to try to minimize the probability of occurrence.
  • B. Update the project management plan to ensure the results of the opportunities are captured.
  • C. Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.
  • D. Log the threats in the risk register to try to maximize the probability of occurrence.

Answer: A

Explanation:
Explanation
After logging the opportunities in the risk register, the project team should also log the threats to minimize their probability of occurrence. This will help in managing both the positive (opportunities) and negative (threats) aspects of risk and ensure a comprehensive risk management approach.


NEW QUESTION # 62
Harold is the project manager of a large project in his organization. He has been actively communicating and working with the project stakeholders. One of the outputs of the manage stakeholder expectations process can actually create new risk events for Harold's project. Which output of the manage stakeholder expectations process can create risks?

  • A. Project document updates
  • B. Organizational process assets updates
  • C. Project management plan updates
  • D. Change requests

Answer: D


NEW QUESTION # 63
......

Verified PMI-RMP exam dumps Q&As with Correct 267 Questions and Answers: https://freedumps.actual4exams.com/PMI-RMP-real-braindumps.html